PDCA 2003 Project of the Year
PDCA Members AET and L.H. Bolduc Help Save Owner $1 Million in Wastewater Treatment Project
Although construction started three months behind schedule, the foundation team made up much of this time by installing several test piles prior to other site activities, by verifying the design-pile capacity could be achieved at shorter driven lengths, and by eliminating the static load test. ...more on this story.